Construction Compliance · California
California demolition permit requirements
- california demolition permit requirements
- demolition permit
- asbestos notification
- general contractors
Policyhold Team, Compliance operations. Practical guidance for GC compliance and mobilization operations.
A California city will not issue a demolition permit from a drawing alone. The building department wants the asbestos notification the air district required, or a declaration that notification does not apply, and then its own permit. On many jobs it also wants a waste plan before debris leaves the site, and weight tickets before final inspection.
This is operational guidance. The city, the air district, and the contract control.
What has to exist before the city will issue the permit?
Treat the permit as a stack, in this order.
- An asbestos survey of the building that will be disturbed.
- The written notification the air district or U.S. EPA required, filed on that district's clock.
- A copy of that notification handed to the city, or a declaration that notification is not applicable.
- The city's demolition permit.
- Where the city requires it, an approved waste plan before hauling, and weight tickets before the job can close.
South Coast AQMD does not issue the demolition permit. The city or county does. The district's role is the survey and the notification. Other air districts write their own rules. The Bay Area Air District is a different agency with a different form and a different clock. Do not file a South Coast packet in a Bay Area city and expect it to count.
What does the asbestos survey and notification actually require?
Health and Safety Code section 19827.5 says a city, county, or other agency that issues demolition permits shall not issue one until it has received a copy of each written asbestos notification the applicant was required to submit to U.S. EPA or a designated state agency under 40 CFR Part 61. The permit can still issue if the applicant declares that notification is not applicable. The city may require that declaration in writing, or it may put the question on the application. Compliance with the state section does not replace federal law.
In South Coast AQMD, Rule 1403 is the worked example.
- A survey report signed by a Certified Asbestos Consultant is required before demolition or renovation. A Certified Site Surveillance Technician may do the survey if a consultant signs the report. A lab sheet by itself is not the survey.
- Building age does not excuse the survey. The district's FAQ says a survey is required even when the building was constructed in the 1980s or later.
- The contractor who will demolish the building files the notification, not an outside helper hired only to submit the form. If the owner hires a new contractor during the waiting period, the clock starts again.
- The notification and fee are due 10 working days, or 14 calendar days, before demolition starts, except for emergencies and ordered demolitions as the rule defines them.
- The district does not send the city a letter that the permit may be issued. Some cities still want their own proof that the notification was received.
If suspect material shows up after abatement, the demolition contractor's job under the South Coast FAQ is to review the survey, confirm no asbestos-containing material remains, and stop if new suspect material appears. Secure it, and tell the owner. Removal is a different license.
Asbestos-related work of 100 square feet or more of asbestos-containing material requires a C-22 Asbestos Abatement classification, or a qualifier who has passed the asbestos certification exam, under Business and Professions Code section 7058.5. Removal contractors also have to be on the Cal/OSHA asbestos registration list, aside from narrow exemptions in the Labor Code. This article does not describe how to remove asbestos.
How is a demolition-only permit different from demolition plus new construction?
A demolition-only permit that is not included with a construction permit sits outside CALGreen. CalRecycle has said for years that jurisdictions should cover those projects themselves if they want the debris recycled. Zero Waste Marin still tells applicants the same thing: call the local jurisdiction.
That does not mean the job is free of paperwork. Cities add the requirement back by ordinance or by permit condition.
- Sacramento County's construction and demolition program lists demolition-only projects among the jobs that must comply, along with new construction and alterations or renovations with a job value of at least $200,000. The county holds final inspection until weight receipts are accepted.
- The City of San Jose's published review page sets a 75 percent diversion rule for construction of a newly permitted structure and for tenant improvements valued at $200,000 or more. Read that page for those project types. Do not assume every demolition in the city is on that list.
- San Leandro's waste form, updated in April 2026, includes demolition-only permits and points applicants at the 2025 code sections 4.408 and 5.408 for the 65 percent floor.
If the same permit covers demolition and the new building, the green building code is much more likely to apply on its own. Ask the building department which permit you are pulling before you promise a diversion rate.
When do the waste plan and the weight tickets show up?
On a covered project, the waste plan is often a permit condition, and the tickets are often a final-inspection condition. The plan names the materials, whether loads will be sorted on site or mixed, the facilities, and whether you will measure by weight or by volume. You do not use both. The tickets are how you prove the plan happened.
A ticket the inspector can use generally shows the date, the facility, the material, the net weight, and the ticket number. Many cities also want the job address, the permit number, or the city of origin on the ticket. A ticket coded as trash, rubbish, or municipal solid waste usually counts as disposed, not diverted. A mixed load taken to a facility the city has not certified often earns no diversion credit.
The details, including Sacramento County's shortfall charge and San Jose's franchise haulers, are in California construction waste requirements.
Hauling offices are usually the ones holding the record the GC has to upload or hand to the inspector. Passport is a free tool for that handoff. A driver opens a personal link and photographs the scale ticket. There is no app to download, and neither the driver nor the GC needs an account. The office keys the tons, date, facility, and ticket number, and the GC opens one link with the certificate and the ready tickets. A confirmed ticket is acceptance of that load. It is separate from subcontractor site clearance. Policyhold does not attest coverage or review exclusions.
Who has to be cleared before the crew mobilizes?
The air-district file and the waste log do not answer whether the demolition contractor or the hauler is allowed on the site. The GC still needs the license, the certificate of insurance, the endorsements the contract calls for, and auto coverage on the trucks that will haul. Those documents expire on their own dates. A current certificate in last year's email is a common reason a crew is turned around on the morning of the job.
What to verify on a subcontractor certificate is covered in subcontractor insurance requirements. Pair that check with the mobilization compliance checklist so field staff are not guessing from a spreadsheet.
Policyhold is the record a GC uses to see which subcontractors are cleared for the job before mobilization. If you want that view on your own vendor list, book a walkthrough.
Why do two California cities treat the same haul differently?
The state statute on the asbestos notification is the same in San Diego and in Sacramento. The waste rules are not. One city certifies mixed-debris facilities and ignores a ticket that lacks the permit number. The next city franchises debris-box companies and will not count a load hauled by someone off that list. A third city is still on the state 65 percent rule and will accept a waste company's documentation in place of a plan you wrote yourself.
Build the packet for the city on the permit, not for "California" in general. When the haul crosses a city line, ask which jurisdiction's facility list and ticket format apply before the truck leaves the scale.
Sources
Operational guidance as of October 2026. The city, the air district, and the contract control.
- California Health and Safety Code section 19827.5
A demolition permit needs a copy of each required asbestos notification, or a declaration that notification does not apply. Findlaw lists the section as current through January 1, 2025.
- South Coast AQMD: Rule 1403 frequently asked questions
Survey, 10-working-day notification, and the statement that the district does not issue the demolition permit. This rule applies in the South Coast district, not statewide.
- Business and Professions Code section 7058.5
C-22 classification or asbestos certification for asbestos-related work involving 100 square feet or more.
- CalRecycle: Construction and demolition diversion informational guide
State 65 percent diversion reference for CALGreen sections 4.408 and 5.408, and the role of local ordinances.
- Zero Waste Marin: Construction and demolition
States that a demolition-only permit not included with a construction permit is outside CALGreen, and tells applicants to check the local jurisdiction.
Frequently asked questions
Quick answers to common questions from GC compliance teams.
Related resources
Construction Compliance · California
California construction waste requirements: the 65 percent rule, the waste plan, and the weight tickets
How California's 65 percent construction waste rule works, what the waste plan must name, and which weight tickets a city will count.
Updated Oct 20, 2026
Read articleMobilization
Mobilization compliance checklist for construction sites
A mobilization compliance checklist for GCs: verify COIs, licenses, and safety docs before subcontractors access the site, with clearance status visible to field teams.
Updated Jun 2, 2026
Read article
See how Policyhold fits your vendor compliance workflow
Walk through COI enforcement, mobilization clearance, and audit-ready records with our team.
Request a demo