Construction Compliance · California

California construction waste requirements: the 65 percent rule, the waste plan, and the weight tickets

By Policyhold Team, Compliance operationsPublished Updated 8 min readSources & references
  • construction waste management plan
  • CALGreen
  • weight tickets
  • general contractors
Share

Policyhold Team, Compliance operations. Practical guidance for GC compliance and mobilization operations.

Covered California projects have to recycle or salvage at least 65 percent of the nonhazardous construction and demolition debris, or meet a stricter local rule. The building department does not take the percentage on faith. It wants a waste plan up front and weight tickets that match the plan before it will close the permit.

This is operational guidance. The city and the contract control. The 2025 California Green Building Standards Code, Title 24, Part 11, has been in effect since January 1, 2026.

What does the waste plan have to name?

Where the city does not already impose a stricter ordinance, nonresidential section 5.408.1.1 requires a construction waste management plan that does four things.

  1. Identify the construction and demolition materials you will divert by efficient use, recycling, reuse on the project, or salvage.
  2. Say whether those materials will be sorted on site or hauled as mixed debris.
  3. Name the diversion facilities that will receive them.
  4. State that diversion will be calculated by weight or by volume, not by both.

Residential section 4.408.2 asks for the same core facts and adds one more: the construction methods you will use to generate less waste. The plan has to be updated as the job changes, and it has to be on site for the inspector.

You can skip writing that plan yourself if you use a waste management company that can document the diversion percentage. For nonresidential work that is section 5.408.1.2. For residential work it is section 4.408.3, and the company has to be one the enforcing agency accepts. The owner or contractor chooses whether a company will do the diverting.

What are the three ways to comply, and what is left out?

For a covered nonresidential project, section 5.408.1 gives three paths. Meet one of them, or meet the local ordinance if that ordinance is stricter.

PathWhat you show
Waste management plan (5.408.1.1)Materials, sort method, facilities, and weight or volume
Waste management company (5.408.1.2)Verifiable documentation that the diverted share meets the section
Waste stream reduction (5.408.1.3)New-construction disposal of no more than 2 pounds per square foot of building area, if the enforcing agency approves

Residential work uses the same idea with different section numbers. Section 4.408.4, marked for low-rise residential buildings, treats landfill disposal of no more than 3.4 pounds per square foot of building area as meeting the 65 percent rule. Section 4.408.4.1 sets an alternative of no more than 2 pounds per square foot. The code's section 301.2 uses a banner to say when a section is low-rise only. The 3.4 pound section carries that low-rise banner. Read 4.408.4.1 in the edition your city adopted before you assume a high-rise building can use the 3.4 pound cap.

Two exclusions matter on a demolition site.

Excavated soil and land-clearing debris are exceptions to the 65 percent calculation in both the residential and nonresidential sections. They are not free material. Nonresidential section 5.408.3 still requires that 100 percent of trees, stumps, rocks, and associated vegetation and soils from land clearing be reused or recycled, with an exception for material contaminated by disease or pests. Stockpiling on a phased project is allowed until that storage area is developed.

Nonresidential sections 5.408.1.1 and 5.408.1.2 also except demolition waste that already meets a local ordinance, or that is calculated against local recycling facilities and markets. That is why a demolition-only permit is not a silent pass. CalRecycle and local programs such as Zero Waste Marin treat a demolition-only permit, when it is not part of a construction permit, as outside the state code. The city then decides. Sacramento County's current program puts demolition-only projects inside its 65 percent rules. The permit application is the document that answers this, not a statewide chart.

There is a further exception where facilities that can hit the rate do not exist, and the residential code also lets the enforcing agency except isolated jobsites beyond the haul range of a diversion facility. Do not invent that exception in the field. Get it from the agency.

What does the inspector accept as a weight ticket?

Section 5.408.1.4 and residential section 4.408.5 require documentation that shows you met the path you chose. Cities turn that sentence into a ticket checklist. A usable ticket generally includes the date, the facility, the material, the net weight, and the ticket number. Many cities also require the project address, the permit number, or the city of origin. If two jobs share one truck, some cities void the ticket for recycling credit.

Two city pages, reviewed in October 2026, show how far local rules move past the state floor.

Sacramento County. Covered projects include new construction, demolition-only, and alterations or renovations with a job value of at least $200,000. Receipts must show material type, tonnage, facility address, and date. Submit tickets for self-haul, subcontractors, franchised haulers, and jobsite clean-up crews. Mixed debris needs a receipt stamped "County Certified C&D Sorting Facility." A mixed load taken to a facility that is not certified does not get diversion credit. Source-separated loads need the receipt to name the material. Wording such as "normal refuse" or "for disposal" does not earn recycling credit. Permits created after September 14, 2026 go through Green Halo, and the applicant uploads a photo of each ticket. Older permits still email receipts to the county. If the job finishes under 65 percent, or receipts are missing, final inspection can wait, and the county may charge a shortfall penalty of $200 per shortfall ton.

San Jose. Municipal Code section 9.10.2480, as described on the city's review page, sets 75 percent diversion for construction of a newly permitted structure and for tenant improvements valued at $200,000 or more. Alternative daily cover does not count. The permit holder may self-haul recyclables to a city-certified facility or use a franchised debris-box company. Only franchised debris-box companies may operate in the city. Weight tickets from the scale house must include the project address or the permit number. Tickets coded MSW, trash, or rubbish get no diversion credit, even though the weight still counts as waste generated. The city tells the general contractor or permit applicant to meet the rule for waste from every subcontractor, and to submit the waste plan and tickets before scheduling final inspection.

The hauling office is the party that sees the scale ticket the same day. Passport is a free way to get that ticket to the GC in a form the waste log can use. The driver photographs the ticket through a personal link. There is nothing to download, and the driver and the GC do not create accounts. The office records net tons, date, facility, and ticket number, and marks the load ready. The GC opens one link that shows the certificate and only the ready tickets, with the photo beside the numbers. A confirmed ticket locks those fields. It is acceptance of that load. It is separate from subcontractor site clearance. Policyhold does not attest coverage or review exclusions.

If the demolition permit itself is the open question, start with California demolition permit requirements.

What never goes into the 65 percent?

Universal waste is not construction debris you fold into the diversion math. Nonresidential section 5.408.2 applies to additions and alterations that meet the scoping rules in section 301.3. Those projects have to show that fluorescent lamps and ballasts, mercury thermostats, and other materials California bans from the trash were disposed of properly and kept out of landfills. The construction documents have to list the prohibited universal waste. The state's reference is the Department of Toxic Substances Control universal waste rule.

Asbestos-containing waste, lead waste, and refrigerants follow their own hauling and disposal rules. A scale ticket from a mixed C&D facility does not document them. Keep those receipts in a different folder from the CALGreen waste log.

Who answers for a subcontractor's debris?

On the San Jose page, the general contractor or the permit applicant is responsible for recycling requirements for all waste generated on site, including waste the subcontractors generate. Sacramento County asks for receipts from subcontractor hauls, not only from the GC's own trucks. If a driver's photo never becomes a ticket with tons, facility, and material, the final hold sits on the permit holder.

That duty is about the debris. It is not the same duty as letting the subcontractor on the site. License, certificate of insurance, endorsements, and auto coverage on the trucks are checked against the contract before mobilization. Subcontractor insurance requirements is the list for that file.

Policyhold is where a GC sees which of those subcontractors are cleared for the job. The waste log will not tell you that a certificate expired last week. If you want to see clearance and the open items on your own projects, book a walkthrough.

Sources

Operational guidance as of October 2026. The city and the contract control. Confirm rates and ticket rules on the permit.

Frequently asked questions

Quick answers to common questions from GC compliance teams.

Not automatically. A demolition-only permit that is not part of a construction permit is outside CALGreen. Cities often require the same waste plan and weight tickets by local ordinance. Sacramento County lists demolition-only projects in its program.

Related resources

See how Policyhold fits your vendor compliance workflow

Walk through COI enforcement, mobilization clearance, and audit-ready records with our team.

Request a demo